What  I am doing now....

After an extended hiatus I'm now back at work on the Big Healey. It's not like I've been entirely idle, but the Jensen-Healey now has a rebuilt and greatly uprated engine, rebuilt and uprated suspension front & rear, odd rust spots fixed and the doors replaced, (it's not entirely done either- I need to weld new metal in on the underside of the front of the bonnet and paint it; and maybe re-wire it, too) and the Rochdale has had a few little things done- sorting out the fuel system (but it too leaves the odd job yet to be done- new upholstery for the seats and a new headliner, minor stuff really; and new carpeting just to make it look really nice...)

I'm giving myself a job to do per month on the Big Healey- something that can be done in a good week-end's work (or two....). So, the plan for the rest of this year and next is:

black on light blue- task DONE!

black on yellow- task TO DO!

Austin-Healey

Jensen-Healey & Rochdale Olympic

January, 2010

  Jensen: Installed shifter extension on transmission.

February, 2010

 

Jensen: Installed transmission on engine. Finished Pedal Box

March, 2010

 

Jensen: Finish minor bodywork & painted & installed hardtop.

Rochdale: Rebuilt & installed transmission, rear hatch stays.

April, 2010

Mount Pillars & Trial Fit Doors, Mount B Pillars; probably need to re-skin the doors....

Jensen: Install engine & transmission with front suspension- fabricate transmission mounts & modify driveshaft.

May, 2010

Trial fit Outer Sills & Rear Shroud, Repair Rear Shroud  

Paint Chassis & Inner Body, Repair Rear Shroud

Jensen: Install Interior & reconnect electrical system.

June, 2010

July, 2010

Mount Front Suspension & Steering, Mount Rear Suspension

Jensen: Final Test, MOT and on the Road!

August, 2010

Install Hydraulics & Fuel System Rochdale: Install new carpet & dye vynil.

September, 2010

  Rochdale: Install voltmeter and fix heater.

October, 2010

Install Wiring & Electrical Equipment Rochdale: Install new headliner and weather stripping.

November, 2010

Paint Exterior Rochdale: fabricate rear engine plate for overdrive gearbox.

December, 2010

Install Interior Rochdale: Rebuild overdrive gearbox.

January, 2011

Install Glass & Dash Rochdale: Install new seats

February, 2011

  Rochdale: Rebuild Metro turbo engine & modify for in-line mounting.

March, 2011

Install Top and Boot Trim Rochdale: Install Turbo engine & overdrive gearbox.
April-Summer, 2012 Rebuild & Install Engine....

Jensen: Rebuild convertible top frame & install soft top. Repair bonnet and rear wings/B Pillars as may be needed.

So, this plan should get me to the end of next year and have an all-but-complete Big Healey except for some relatively minor trim installation and the rather more significant and expensive rebuilding of the engine and its installation. I have virtually all of the non-engine mechanical components and other bits & pieces. The only thing that will cost non-trivial money is the interior, but if I set £100 aside a month between now and when the time comes to do it I'll nearly have enough with what's already in the kitty.... But mid-2011 will then get really serious financial cash flow issues with the Engine components & rebuild work... how fast do I want to go? Of course, I could put a relatively stock (= cheaper) engine in and get it on the road, and acquire a second engine (as I did originally, but sold to help financing the rest) to rebuild at leisure to a more sporty specification.